What is a scope of works – and why do you need one?
A scope of works is a written list of everything a building job involves, trade by trade and item by item. It's the single most useful document for getting builders' quotes you can compare – and for avoiding nasty surprises later.
Why quotes differ so much
Ask three builders to price the same extension from the drawings and you'll often get three very different numbers. Usually that's not because one is cheap and one is greedy – it's because each has priced a slightly different job. One has included the kitchen, one hasn't. One has allowed for drainage, one assumes it's straightforward. One has a skip in the price, one will charge for it later.
Drawings show what the finished building looks like. They don't list the work needed to get there. A scope of works fills that gap.
What a good scope of works includes
- Every trade section, in order – preliminaries, demolition, foundations, drainage, walls, roof, windows, electrics, plumbing, plastering, joinery, finishes, decoration and external works.
- Quantities – how many square metres of wall, metres of foundation, number of sockets – so everyone prices the same amount of work.
- Specification – what the work is: "100mm insulated cavity wall, brick to match existing", not just "walls".
- Who supplies what – kitchens, sanitaryware, tiles and flooring are often supplied by the homeowner. Say so clearly.
- Provisional sums – fixed allowances for things not yet chosen, like £12,000 for a kitchen, so every builder includes the same figure.
- Exclusions and assumptions – what isn't included, and what has been assumed (for example, foundation depth).
How to use it with builders
- Send the same scope of works to every builder, with your drawings.
- Ask them to price against each line, and to list anything they think is missing.
- Compare totals and trade sections. A section that's far higher or lower than the others is worth a question.
- Once you choose a builder, attach the priced scope to your contract. It then becomes the definition of what you're paying for – and makes extras much easier to agree.
Who writes a scope of works?
Traditionally an architect or quantity surveyor writes it, often for several hundred pounds or more. Some builders write one as part of their quote – but that's their scope, not yours, which makes comparison harder.
PlansToPrice writes one from your drawings in minutes. Every paid estimate includes the full measured scope with prices, plus a builder version with the prices removed – as a PDF and an Excel sheet builders can price directly – so you can send exactly the same list to everyone you ask to quote.
Related: see a sample estimate · cost guides